Is Movement type-201 allowed Material values to enHi friends,I have a different scenario.During posting of Materials to cost centre normally we allowed to enter qty,cost center.As per my present requi
网友回答
Hi,Q1.after PO or STO ,during GR / GI,is it possible to enter the value of the materials in MIGO or not?No,it is not feasible as the issued stock will be valuated at the latest MAP or standard price of the material master at the time of GI.Q2.I know that MIGO GI Movement type 201 allow me to enter cost centre and the material quantity only.Using TC = OMBW / OMWB in the field status activation,Can we activate value field ,so that I can enter value of the material.Is SAP have such facility?No,it is not supported in SAP.Q3.As per my knowledge,during PO stage and Invoice verification stage only we can do the price /value updating.During GR/GI stage we cannot do Value / Price updating.Correct me if I am wrong.It is correct.Cheers,HT 查看原帖>>